|
6.33
|
Load factor billing
As opined by some of the objectors, it is true
that it is the statutory obligation on the part of the licensee
to replace meters. Load factor billing has been prescribed
for a limited period the meter remains defective/or the
consumer goes without meter to serve as a disincentive for
the consumer and help adoption of metering by consumers.
Hence, the Commission directs that the load factor billing
should continue as per the existing tariff.
|
|
6.34
|
Incentive for maintaining
high power factor
|
|
6.34.1
|
For the first time, the Commission
in its tariff order dt.30.12.99 introduced an incentive
to encourage improvement in power factor above 90%. Subsequently,
the limit was raised to 97% in the RST order dt.19.01.2001.
WESCO estimates that the rebate alone on this account to
HT/EHT consumers will be of the order of Rs.1.31 crore during
the FY 2001-02.
|
|
6.34.2
|
Some objector opined that for
the health of electrical machinery it is risky to maintain
power factor between 97% and unity power factor lagging
because there is every chance of high voltage when suddenly
some load gets off from the circuit.
|
|
6.34.3
|
It should be kept in view that
the industries for better protection of their installation
should follow prudent operational practice installing protective
devices, so as to isolate the equipment during abnormal
transient condition arising out of sudden load throw off
or tripping of meter or feeders.
|
|
6.34.4
|
Further, as indicated below
the KVA demand of the industry decreases as the PF improves,
there by benefiting the consumer on account of higher demand
charge.
PF
KVA
Excess KVA
201
1
0
0.99
1.01
0.01
0.98
1.02
0.02
0.97
1.031
0.031
0.96
1.042
0.042
|
|
6.34.5
|
Similar provision of power factor
incentive/rebate have been recommended by other State Regulatory
Commissions such as Gujurat Electricity Regulatory Commission,
U.P. Electricity Regulatory Commission, Maharashtra Electricity
Regulatory Commission where incentive is allowed for maintaining
PF above 95%. Hence, the Commission does not consider it
necessary to make change in the existing provision with
regard to power factor incentive.
|
|
6.35
|
Incentive for prompt payment
|
|
6.35.1
|
Some objectors suggested for
relaxation of the rebate period of 48 hours. WESCO in its
RST application for the year 2001-02 has estimated that
the rebate on account of prompt payment within 48 hours
of presentation of bill during the FY 2001-02 will be order
of Rs.2.1crore in addition to an amount of Rs.0.5 crore
on account of rebate of 10 paise/unit. Hence, it is expected
that to avail such heavy amount of rebate, consumers should
put extra efforts and make payment of bills in time.
|
|
6.35.2
|
As per Commission's order, certain
categories of consumers are entitled to a rebate of 1% of
the amount of the monthly bill (excluding arrears and electricity
duty) if payment is made within 48 hours of the presentation
of the bill. When a cash discount is allowed for payment
within a specified period, the cost of credit can be computed.
For instance, if 15 days credit is offered with a stipulation
of 1% cash discount for payment within 48 hours (two days),
excluding the day for service of the bills, it means that
the cost of deferment of payment by 12 days is 1%. If payment
is made 12 days earlier than the due date, 1% of the amount
can be saved, which amounts to an annual attractive saving
rate of 30%.
|
|
6.35.3
|
If cash discount is not availed,
the effective rate of interest will work out to 30.3%. The
rational for availing trade credit should be it's saving
in cost over the form of short term financing, its flexibility
and convenience. Stretching trade credits or accounts payable
results in cash discount foregone.
|
|
6.35.4
|
As an example, Mahanadi Coal
Field with a monthly bill of Rs.8 crore gets a rebate of
Rs.8 lakh per month or nearly a crore of rupees over a period
of one year. It is in the interest of the consumer to avail
the cash benefit or pay the normal charges i.e. within 15
days from the date of bill.
|
|
6.35.5
|
This practice of prompt payment
is followed by the generators for raising bills against
GRIDCO and by GRIDCO to DISTCOs also. In this age of SATCOM,
FAX, Internet and STD commercial benefits must dictate and
guide not only the functioning of the licensee but those
of the consumers also.
|
|
6.35.6
|
It has been reported by the
licensees that a number of consumers are availing this prompt
payment rebate. The objections have come mostly from the
various Departments of the Government for fear of audit
objections for not availing the rebate due to their cumbersome
official procedure within their organization before releasing
payment for consumption of electricity. For them 48 hours
may not be adequate and they may not be able to avail the
prompt payment rebate. In that case, they can pay the normal
charges within the due date of 15 days and convince the
audit about their difficulty of not availing the rebate
or alternatively streamline the procedure to avail the rebate
as a commercial incentive for the Government
|
|
6.35.7
|
In view of this, the Commission
does not consider it necessary to depart from its past order
regarding incentive on prompt payment.
|
|
6.36
|
Metering of street lights
|
|
6.36.1
|
Issues that street light metering
has not been done and billing is done on load factor basis
was raised during the course of the hearing. In this regard,
Commission would like to convey that meetings were taken
by this Commission with Director, Municipal Administration,
Government of Orissa, Chief Executives of Municipalities
and Managing Directors of DISTCOs on 11.04.2001 and 19.04.2001
to resolve the issues on metering of street lights.
-
It was agreed in the meeting
that inspection to assess the connected load would be
taken up by Municipality and DISTCOs.
-
A single agreement for street
lighting will be executed for a municipal area.
-
Wherever metering is in place,
the rates applicable for street lighting category should
be implemented.
-
Until metering is in place,
calculation of consumption for the purpose of billing
will have to be mutually worked out by the municipalities
and DISTCOs considering the connected load and the number
of burning hours for street lighting. Preferably average
11 hours burning of the lamps may be adopted due to seasonal
variation. No maintenance should be carried out during
day time which requires avoidable consumption of electricity.
-
The switching ON and OFF of
street lights will be done by the staff of the licensee.
Replacement of bulbs, fittings and maintenance thereof
shall be carried out by the municipal staff.
|
|
6.36.2
|
The licensees should take adequate
steps to comply with the decisions taken in the joint meeting
with the Director, Municipal Administration, Government
of Orissa and Chief Executives of Municipalities, as stated
above.
|
|
6.37
|
Industrial policy framed
by Government of Orissa
An issue was raised by the Orissa Small Scale Industries
Association that the proposed amendment in tariff by the licensee
is directly against the Industrial Policy Resolution (IPR)
of Government of Orissa. This is clarified that Industrial
policy differentiating categories and conferring benefits
change from time to time on various considerations. Electricity
charges are to be non-discriminatory from economic point of
view and it is neither desirable nor possible to synchronize
the pricing in keeping with changes from industrial and financial
angle. However, if the State Government desires to extent
any benefit to a class or group of consumers, they can do
so under Section 12(3) of OER Act, 1995 by providing subsidy.
|
|
6.38
|
Retaining of Security Deposit
by licensee
|
|
6.38.1
|
The objection raised by some
objectors (OCA) that bi-monthly domestic bills are increasing
loss to the licensee is not correct as the licensee is already
retaining charges of supply of two months against security
deposit which can be utilized as working capital.
|
|
6.39
|
Multi-year Tariff
|
|
6.39.1
|
In course of the hearings, the
utilities as well as some of the respondents spoke about
the element of uncertainty and risk inherent in an annual
tariff setting exercise and they pleaded for introduction
of a multi-year tariff regime which would reduce such uncertainty
and bring in predictability. We, too are conscious of the
need for greater certainty in the regulatory treatment of
a host of issues having direct impact on tariff setting.
It shall be our endeavor to set in motion a multi-year tariff
regime effective from April, 2003 for FY 2003-04 after wide
publicity and valued consultation with all the stakeholders.
We have, in fact, initiated preparation of a five-year sectoral
plan covering generation, transmission and distribution
which will provide key inputs to this exercise. The draft
consultation document which is currently under finalisation
will also be brought out to facilitate the process of such
consultation and obtain comments from the various stakeholders.
|
|
6.39.2
|
The utilities have to improve
upon their own performance within a stipulated time frame
by upgrading their managerial skills and efficiency by scrupulously
adhering to certain operational norms like reduction in
the level of loss, attaining certain level of billing and
collection efficiency, setting a target for investment and
avoiding time and cost overruns in execution of projects,
etc. This calls for fixing a target to be achieved over
a "Control period" than a target confining to a single year
to provide a kind of predictability to the consumers, their
own shareholders and to the Regulatory Commission. The Commission
considers it prudent and desirable to go for a multi-year
tariff regime for which the utilities should conform themselves
to a multi-year target setting in the areas stated above.
We also feel that the FY 2001-02 should be considered as
the base year for all calculations as suggested by the Kanungo
Committee.
|
|
6.39.3
|
Some objectors raised the issue
that the licensee should accept the payment by account payee
cheque instead of demand draft.
|
|
6.39.4
|
As per the existing provision
in OERC Distribution Code, 1998 (Regulation 1993), the bill
amount shall be paid by the consumer either in cash or by
bank draft or by banker's cheque or where specifically allowed
by the licensee by account payee cheque or credit cards.
Hence, the facilities are already available in the OERC
Regulation.
|
|
6.39.5
|
Some of the objectors advocated
in favour of uniform retail tariff throughout the state
. Historically, uniform tariffs have been used in Orissa,
and indeed in all states of India, in spite of significant
cost differences to serve different geographic areas. Prices
that differ in relation to differences in cost generally
make better use of society's resources than uniform tariffs.
|
|
6.39.6
|
Some objectors suggested for
reduction of cross subsidies. As has already been dealt
in the Retail Supply Tariff order of the Commission dated
19.01.2001, the tariff structure that this Commission inherited
was a highly distorted one. In the past years by rationalising
the tariff structure it has been ensured that there is a
progressive increase in the rate of tariff for those who
are paying less than the average cost of supply. The Commission
in future tariff revisions will take steps for rationalization
of tariff i.e. gradually adopting a uniform rate for all
consumer categories using electricity on the same voltage
of supply which is a good measure of the cost of supply
or thereby reduce the cross subsidy between groups of consumers.
|
|
6.39.7
|
The question of a reasonable
railway traction tariff raised by the S.E. Railway so as
to maintain a railway traction tariff, not exceeding that
of HT industrial consumer was also highlighted for consideration
by OERC. The Commission would like to clarify that the railway
traction tariff in Orissa is at par with that of HT or EHT
consumers depending upon the voltage of supply as the tariff
structure has been totally linked to the voltage of supply.
Railway traction tariff is lower in Orissa. Therefore railways
should have no grouse on this account.
|
|
6.39.8
|
The railways had also raised
the issue of a single part tariff which is today applicable
only to very large industries with a guaranteed off-take
to which category the railways does not belong.
|
|
6.39.9
|
The second issue relates to
the prevalent maximum demand charge in Orissa. It needs
to be clarified that the Commission does not propose to
make any change to the current maximum demand charge in
force. Railway further concern about recording and charging
of maximum demand for individual supply points as per the
existing system turned out to be totally unrealistic as
the railways were moving loads for all substations along
this track. In this connection, the Railways quoted the
letter of Ministry of Energy CEA, New Delhi dated 21.10.1988
proposing billing on the basis of simultaneous maximum demand
recorded in contiguous substation of the SEBs. It may be
mentioned here that the railway traction supply is from
the EHT network of the GRIDCO and the billing is done by
the various supply companies to the railways in their area
of license. Therefore, the Commission is of opinion that
the issue should be mutually discussed by the railways with
the four distribution companies and their views on the matter
may be placed before the Commission for taking a holistic
view.
|
|
6.39.10
|
The railways also proposed that
the integration period of 30 minutes for measurement of
maximum demand in respect of railway traction has been changed
to 15 minutes. The railways requested that the OERC may
consider restoration of integration period 30 minutes as
per the earlier method which is also in confirmity with
the clause No.2(8) of Electricity Supply Act, 1948.
|
|
6.39.11
|
The Commission deliberated on
this issue and observed that 30 minute integration period
for all categories has been provided in the Regulation of
ASEB, Ahmedabad Electricity Company, MPSEB, HSEB, DVP, Gujurat,
Maharashtra, Tamil Nadu. Fifteen minute integration period
has been provided by UPERC, APERC for loads more than 4000
KVA, and for railway traction by WBSEB. There are SEBs with
one hour integration period also.
|
|
6.39.12
|
The railways earlier have made
a case that there can be growth of traction only if the
cost of tariff matches the cost of diesel locomotion. Keeping
this fact in view, the Commission will consider favourably
the adoption of 30 minute integration period which can reduce
the overall tariff for railways. It will be, therefore,
desirable to discuss the issue along with the issue of simultaneous
maximum demand due to feed extension for meeting the demand
of the rolling stocks after discussion with the various
supply companies of the state. The railways and DISTCOs
may mutually discuss and come up with a proposal for consideration
of the Commission. This will require amendment of the supply
regulation OERC Distribution (Condition of Supply) Code,
1998. Till such time the present arrangement shall continue.
|
|
6.40
|
Consumer Service
|
|
6.40.1
|
Construction Power
Objection was raised by M/s. Aditya Aluminium that
the industries under construction may be classified separately
and no demand charge should be levied on construction power.
There seems to have no logic behind the objection as the
licensee is to arrange/book, the quantum of power as per
the contract demand and pay fixed charge against the said
quantum of power which he has to recover from the consumer.
|
|
6.40.2
|
Observations for over
drawal penalty clause
For the purpose of calculation of minimum demand
there should not be any differentiation between peak or
off peak hours. As such we do not accept the proposal of
the objector for any change in existing tariff order.
|
|
6.40.3
|
Observation for incentive
higher consumption
|
|
6.40.3.1
|
Some objectors such as M/s.
Mahanadi Coal fields Ltd. pleaded that load factor as per
standard nomenclature should be based on Maximum Demand
and should have no relation with Contract Demand.
|
|
6.40.3.2
|
It is clarified that, for the
purpose of calculation of incentive energy, the standard
terminology of Load Factor has not been used, rather it
is only the ratio of the total number of units consumed
during a given period to the total number of units that
would have been consumed had the contract demand or the
maximum demand whichever is higher was maintained through
out the same period.
|
|
6.40.3.3
|
It may be noted that the incentive
tariff for HT/EHT category of consumers was introduced in
the OERC RST order dt. 30.12.99 where incentive energy was
considered above the load factor of 50% of contract demand.
Further as mentioned in the OERC RST order dt. 19.01.2001
"Some objectors objected to recording of load factor during
the FY 1999-00 in excess of 100% in the filing made by the
licensee on the ground that it had an element of absurdity.
As prescribed in OERC Condition of Supply Regulation, 1998
load factor of a consumer under no circumstances can exceed
100%" Therefore consumption ratio was adopted in place of
load factor for determination of incentive energy. It is
further clarified that for the purpose of calculation of
incentive energy, power factor should be taken as 0.9 for
conversion from KVA to KW or MVA to MW.
|
|
6.40.4
|
Treatment of Past Losses
|
|
6.40.4.1
|
With regard to the treatment
of past losses, the Commission would like to clarify that
in the absence of audited accounts of the licensees, it
is difficult to determine the extent of loss that could
have been admissible within the provisions of the Sixth
Schedule to the Supply Act, 1948. A decision on this issue
can be taken only when the accounts are compiled and audited
in accordance with the relevant regulations of OERC.
|
|
6.40.4.2
|
The Commission observes with
displeasure about non-maintenance of the asset register
by licensees inspite of its earlier direction. The Commission
directs that maintenance of asset register must be completed
latest by 31 August and compliance reported
|
|
6.40.5
|
Demand charges during
statutory power cut
The levy of demand charge during the period of
statutory power cut has to be dealt in accordance with he
relevant conditions of OERC (condition of supply) Code,1998.
|
|
6.40.6
|
Meter Rent
The Commission examined the issue of rents chargeable
for the meters supplied by the licensee and does not consider
it necessary to make any change the rate already fixed by
the Commission in its order dtd.19.01.2001.
|
|
6.40.7
|
Quality of Supply &
Service
Interruption, low voltage and unreliable supply
is a matter of serious concern to the Commission which is
taking appropriate steps to verify the data furnished by
the licensee in this regard through an affidavit to the
Commission. The Commission also is taking effective steps
for monitoring of these parameters for meeting the supply
standards as prescribed by it.
|
|
6.40.8
|
Unauthorised and Illegal abstraction
of electricity
The issue of unauthorised abstraction of electricity is
one of the principal causes of high commercial losses in
the licensee's system which is being monitored every month
at the Directors' Level Meeting. The licensees must take
the help of law and order authorities and the Commission
is committed to allow any additional expenditure on account
of curbing the theft and unauthorised abstraction of electricity
which must be taken up vigorously and it shall continue
to be monitored at the Commission's level.
|
|
6.40.9
|
Rural Electrification
The rural electrification work to be taken up by
the licensee as a capital grant. In this connection, the
Kanungo Committee have suggested for setting up of Rural
Engineering, Planning Organisation (REPO) and Rural Electrification
Planning Units (REPU) under Government of Orissa to monitor
R.E. and L.I. works. As and when REPO AND REPU start functioning
it is believed R.E. & L.I. works will be expedited.
|
|
6.40.10
|
Special Tariff for Power
Intensive Industries
|
|
6.40.10.1
|
The Commission has taken a decision
to continue with the tariff structure approved vide its
tariff order dtd.19.01.2001 in respect of all categories
of consumers supplied by the distribution and retail supply
licensee. In this connection, the Commission also examined
the issues regarding a special tariff of the power intensive
categories of industries. Some of the objectors also submitted
that a preferential treatment to the EOUs was a burden to
a licensee and the general consumer, as costly power has
to be procured to meet such demand. The Commission reiterate
its commitment for rationalisation of the tariff structure
linked to the voltage of supply. Keeping the above objective
in view, incentive tariff has already been introduced for
consumers of contract demand of 110 KVA and above available
power supply at HT or EHT in the previous tariff orders.
That automatically reduces the per unit cost of electricity
with a higher level of consumption as the fixed cost in
the form of maximum charge gets distributed over a larger
number of units.
|
|
6.40.10.2
|
The Commission however, has
taken note of very special nature of some of the industries
who provide continuous high load factor to the system and
in the process provides a support during the off-peak hours
as base loads besides dissuading such units from setting
up CPPs. On the other hand this helps in getting cross subsidy
from such classes of consumers to other classes of consumers
who are charged below the level of cost of supply. This
has also to be weighed against the option of having an industry
within its fold of supply of a licensee with a lower profit
margin and the option of not having the industry at all.
The Commission has favourably considered in the past the
above option and have allowed signing of special agreement
with a proposal of guaranteed off-take at a rate lower than
the normal rate applicable to similar class of industries.
|
|
6.40.10.3
|
The Commission in its past orders
had approved tariff for consumers with a contract demand
with 100 MVA and above with a guaranteed load factor of
80% @ 200 paise/unit without levy of any demand charge.
The Commission has approved a rate of 182 paise/unit with
a guaranteed load factor of 90% and a contract demand of
50 MW in respect of INDAL by approving for entry into special
agreement between INDAL and WESCO. This rate is linked to
the Bulk supply Tariff approved in the Commission's order
dtd.19.01.2001. This rate will undergo a change on account
of revision in Bulk Supply Tariff.
|
|
6.40.10.4
|
The Commission will examine
such special agreements for approval as and when it is placed
before the Commission provided the rates are within the
parameters indicated above.
|
|
6.40.10.5
|
Any licensee willing to enter
into special agreement with a rate other than that for a
particular category can do so provided the licensee undertakes
to absorb the difference between the revenue at the approved
rate and the rate at which it proposes to enter into a special
agreement with any industry. However, entry into special
agreement should be non-discriminatory in nature i.e. consumers
falling into same category should be offered similar rates.
|
|
6.41
|
Emergency power supply
to CPPs
The Commission examined the request for raising
the level of emergency power availability to 75% of the
capacity/co-generation plants to reduce the burden on the
smaller industries. The Commission would like to clarify
that in the tariff order dtd.19.01.2001, a rate of 380 paise/unit
has been fixed for emergency power supply to CPP. The order
does not stipulate levy of any demand charge for emergency
power supply to CPPs.
|
|
6.42
|
The revenue requirement estimated
by WESCO has been duly examined at the Commission's end.
|
|
6.43
|
Corrective measures
and alternative calculation of revenue requirement
|
|
6.43.1
|
During the tariff hearing the
State Government did not appear and participate despite
due services of notice. It even failed to attend the Commission
Advisory Committee Meeting in this connection. The Commission
has received no assistance or commitment from the State
Government and has had to proceed in the absence of Government's
participation. It may be mentioned that during the Workshop
on 09.01.2000, organized by the Department of Energy, Government
of Orissa, the Commission made a presentation elaborating
the various corrections as outlined in para 6.43.6 (A) below.
In the circumstances, the Commission has been constrained
to recommend several measures as listed below for approval
by the Government of Orissa w.e.f. 01.04.2001 to bring down
the cost of power, cost of transmission of GRIDCO and cost
of distribution. In view of the urgency and importance of
the measures for consumers of the State and for the electricity
industry and success of the State policy of reforms, it
is absolutely essential that the State Government should
communicate their decision on the recommendations without
delay, in order that the Commission may give effect to the
alternative calculation of revenue requirement. Everyday
of delay causes huge avoidable cost to the consumers and
the revenue gap of the licensees will go on snowballing
beyond control.
|
|
6.43.2
|
The terms and conditions for
purchase of power from OHPC by GRIDCO is governed by the
power purchase agreement between OHPC and GRIDCO. The interim
PPA between OHPC and GRIDCO for purchase of power from OHPC
old stations upto 31 March 2001 has been approved by OERC
with certain observations. Both OHPC and GRIDCO have been
directed to submit the PPA to OERC for approval. The new
PPA in respect of these stations effective from 01.04.2001
has not yet been received till date. Based on the latest
commercial practice OERC directs that parameters like O&M
escalation, return on equity and depreciation in respect
of these stations will be calculated in accordance with
the norms given in this order. The Commission also decides
to apply lower rate of depreciation (pre-92 rates) for transmission
and distribution assets to bring down the cost of supply
to the consumer.
|
|
6.43.3
|
Similarly the Commission would
like to depart with respect to the O&M escalation, ROE
and depreciation norms in respect of UIHEP to bring down
the input cost of power.
|
|
6.43.4
|
(a) OHPC old stations
-
O&M escalation taken
as per the weighted average of growth of Wholesale Price
Index and Consumer Price Index for FY 2001-02 which
works out to 2.5%. The same rate has been adopted for
FY 2002-03.
-
Return on Equity is calculated
@ 12% on OHPC's own investment of Rs 22.56 crore.
-
Depreciation has been
allowed to the extent of loan repayment during the year.
(b) UIHEP
-
O&M escalation taken
as per the weighted average of growth of WPI and CPI
for FY 2001-02 which works out to 2.5%. The same rate
has been assumed for FY 2002-03.
-
ROE has been calculated @12%
on equity of Rs.298.70 crore.
-
Depreciation has been
allowed to the extent of loan repayment during the year.
(c) GRIDCO & DISTCOs
Depreciation has been calculated at pre-92 rate for
years 2001-02 and 2002-03 both in respect of transmission
and distribution business.
|
|
6.43.5
|
The Commission is entrusted
with heavy responsibility as per Section 11 of the OER Act,
1995 under the head "Functions of the Commission". It would
be appropriate to quote the relevant portion of the above
section.
"11(1) Subject to the provisions
of this Act, the Commission shall be responsible to discharge,
amongst others, the following functions, namely-
-
to aid and advise, in
matters concerning generation, transmission, distribution
and supply of electricity in the State ;
-
to regulate the working
of licensees and to promote their working in an efficient,
economical and equitable manner;....
|
|
6.43.6
|
(A) In view of the above
provisions, the Commission would be failing in discharging
its responsibilities without giving proper advice to the
State Govt. for adopting the corrective steps to bring the
reforms back to rails. Commission has applied the following
correctives in determining the revenue requirement for FY
2001-02 and 2002-03:-
-
Interest on GRIDCO bond
issued by DISTCOs for the power purchase loan liabilities
has been calculated @8.5% for FY 2001-02 and FY 2002-03
-
Interest on World Bank
loan has been calculated in terms of its original sanction
treating 70% as loan and 30% as grant for FY 2002-03
-
Interest on all existing
bonds issued by GRIDCO have been calculated @8.5% for
FY 2001-02 and FY 2002-03 assuming resecuritisation
of the same.
-
New bonds of Rs.638 crore
to be issued against power purchase liabilities of CPSU's
as on 28.02.2001 have been calculated @8.5% for FY 2002-03.
-
Impact of zero coupon
bonds of Rs.400 crore issued by GRIDCO to Government
of Orissa against upvaluation of assets has not been
considered for FY 2001-02 and FY 2002-03.
-
Outstanding loans from
REC and PFC have been assumed for resecuritisation with
a tax free rate of 8.5%.
-
In view of swapping of
Government and GRIDCO dues, interest on Government loan
of Rs.168.71 crore has not been allowed as a pass through
for FY 2002-03.
-
Interest on GOO loans
has not been allowed arising out of upvaluation of OHPC
assets.
-
GOO loan of Rs.576.57
crore has been treated as loan on perpetuity.
(B) The Commission therefore
advises Government of Orissa under section 11(1)(a) of the
OER Act, 1995 to approve the correctives w.e.f. 01.04.2001
as outlined in this para from (i) to (ix) above to bring
down the cost of power for the year 2001-02 and 2002-03.
|
|
6.43.7
|
In this context the Commission
deems it fit and proper to review the whole question of
revaluation of the assets of the erstwhile OSEB and Government
of Orissa, at the time of revesting of the same with GRIDCO
and OHPC and the impact of the revaluation on the tariff
to be fixed now and in future. At the time of revesting
GRIDCO and OHPC were wholly owned Government companies.
Section 23(4) of the OER Act, 1995 did not require any such
revaluation. When the assets of the OSEB vested in the State
Government, the State Government paid nothing for it and
did not incur any expenses. The revaluation seems to have
been purely notional, agreed to between State Government
on the one hand and GRIDCO and OHPC on the other hand, the
latter being Government companies at that time. Clause 2
of the statutory orders dated 01.04.1996 vesting assets
with GRIDCO and OHPC runs as follows.
"In accordance with section
24 of the Act, the fair value shall be duly determined
of the property or rights in the undertaking involved
at the time of transfer to or involvement of any person
or body other than the wholly owned Government company
or companies."
No such fresh and due determination
of fair value appears ever to have been done - not even
at the time of involvement of DISTCOs operating under the
aegis of private investor. There may have been some reason
(like credit worthiness of GRIDCO and OHPC), at the material
time, for state and GRIDCO/OHPC agreeing to some notional
revaluation, but the Commission does not think any such
reason to be relevant for the purpose of tariff setting,
involving rights of consumers and third parties or useful
in the context of present realities in the industry. The
Commission therefore in the public interest has attempted
to nullify the effects of revaluation in the present tariff
setting.
|
|
6.43.8
|
Based on the observations of
the preceding paragraphs of this order and prudent commercial
consideration relying on the existing purchase power agreements,
relevant rules, orders and evidential documents placed before
the Commission. The Commission determine the revenue requirement
for the FY 2001-02 as well as for the year 2002-03. Accordingly
the revenue requirement as estimated in two scenarios (i)
with correctives (ii) without correctives for 2001-02 is
given in Table : 23. Details of calculation of revenue requirement
is given in Annex-A1.
Table : 23
(Rs. in Crore)
|
Name of the licensee
|
2001-02 (With correctives)
|
2001-02 (Without correctives)
|
Proposed sale in MU
|
|
CESCO
|
775.00
|
777.83
|
2461.48
|
|
NESCO
|
435.44
|
444.00
|
1194.87
|
|
WESCO
|
556.08
|
562.09
|
1756.19
|
|
SOUTHCO
|
316.60
|
323.52
|
901.47
|
|
Additional RR on account
of change in cost of power and transmission by GRIDCO
|
|
301.28
|
|
|
Total for DISTCOs
|
2083.12
|
2394.34
|
6314.02
|
|
|
6.43.9
|
The revenue requirement for
FY 2002-03 in both the scenarios (i) with correctives and
(ii) without correctives as per our recommendation regarding
cost of power and cost of transmission based on the principles
enunciated in the earlier paragraphs of this order is given
in Table : 24. Details of calculation of revenue requirement
is given in Annex-A2.
Table : 24
(Rs. in Crore)
|
Name of the licensee
|
2002-03 (With correctives)
|
2002-03 (Without correctives)
|
Difference
|
Proposed sale in MU
|
|
CESCO
|
767.34
|
918.85
|
151.51
|
2768.03
|
|
NESCO
|
421.62
|
509.25
|
87.63
|
1329.36
|
|
WESCO
|
559.43
|
670.63
|
111.02
|
1980.13
|
|
SOUTHCO
|
327.51
|
393.81
|
66.30
|
1078.58
|
|
Total for DISTCOs
|
2075.90
|
2492.54
|
416.64
|
7136.10
|
|
|
6.43.10
|
It is evident from the calculations
given in Table above that it will require a very stiff upward
revision in Retail Supply Tariff in respect of all consumers
of the State if the correctives proposed by the Commission
is not accepted by the government for immediate implementation.
Incidentally, the correctives applied by the Commission
are, by and large, in line with those of Kanungo Committee
recommendation with minor modifications and few additional
measures.
|
|
6.43.11
|
In this connection, the recommendation
of the Kanungo Committee is very pertinent wherein they
had advised an external financial support other than debts
to the tune of Rs.3240 crore during a transition period
of 4 years from 2001-02 to 2004-05 to keep the tariff structure
static at the current level and proposing to raise it by
about 18% in the year 2005-06. It is expected that the Government
will consider the advice of the Commission in this regard
and take immediate steps so as to avoid a stiff rise of
tariff to all classes of consumers particularly when State
Government may not be in a position to provide financial
support as contemplated in the Kanungo Committee report.
|
|
6.43.12
|
However, if the decision of
the Govt. of Orissa goes contrary to the advice tendered
by the Commission, the revenue requirement for the FY 2001-02
and 2002-03 as determined without applying the correctives
shall be due for recovery from the consumers.
|
|
6.44
|
Expected revenue from
charges
The expected revenue from charges in respect of
all the DISTCOs have been determined by the Commission as
explained in para 6.9.5.2 of this order in Table 15 &
16.
|
|
6.45
|
For the purpose of RST 2001-02,
the licensee has given a proposal which is given in annex
to this order.
|
|
6.45.1
|
In para 6.43.8 the revenue requirement
has been calculated by applying necessary correctives to
power and transmission cost payable to GRIDCO and distribution
cost.
|
|
6.45.2
|
Any revision of tariff in accordance
with the OER Act, 1995 can be applied prospectively. The
reason is that a clear seven day's notice before its implementation
is necessary under Sec. 26(5) of the OER Act, 1995. Revision
of tariff cannot be done in case of the FY 2001-02, which
is already over. This situation arose because of deficiencies
on the part of the licensees to submit the revenue requirement
and tariff application in complete shape in time. As such,
the tariff revision proposal for the year 2001-02 submitted
by the licensee is rejected.
|
|
6.45.3
|
As observed in para 6.43.12
if the decision of the Govt. of Orissa goes contrary to
the recommendations made by Commission the revenue requirement
for the year 2001-02 as determined in this order without
applying the correctives shall be due for recovery. Since
the FY 2002 is already over and no fixation of tariff is
possible with retrospective effect, the Commission will
treat the gap between the revenue requirement and expected
revenue for the FY 2001-02 as a regulatory gap for recovery
at a future date.
|
|
6.45.4
|
In as much as tariff proposals
for FY 2001-02 have been rendered infructuous, GRIDCO and
DISTCOs propose that the Commission proceed under Section
26 (6) of the OER Act, 1995 to determine tariff for FY 2002-03
on the basis of revenue requirement for that year as approved
by the Commission. Hence the Commission has proceeded under
section 26(6) to determine tariff under section 26(6) of
the OER Act, 1995 for the FY 2002-03.
|
|
6.45.4.1
|
The Commission have made several
recommendations to the Government of Orissa for their implementation
w.e.f. 01.04.2001. Accordingly the Commission have determined
the Retail Supply Tariff applying all correctives based
on its recommendations to the Government. If a decision
to the contrary is taken by the Government the revenue requirement
for the FY 2002-03 as determined without applying the correctives
shall be due for recovery from the consumers. It will raise
the revenue requirement by Rs.416.64 crore on the basis
of our present estimate. A tariff schedule is given in the
Annex-D3.
|
|
6.45.5
|
This is based on the assumption
that the existing retail supply tariff as approved by OERC
in order dated 19.01.2001 shall continue upto 31.07.2002
and the rates indicated in Annex-D3 shall be valid
from 01.08.2002 to 31.03.2003 provided the recommendation
as indicated earlier are not accepted by the Government
latest by 15 July 2002.
|
|
6.45.6
|
This tariff effective from 01.08.2002
shall be subject to such proportionate reduction as may
be necessary to the extent the Government accepts the recommendation
made by the Commission. The reductions being purely arithmatical
in nature shall take effect without any further proceeding
for amendment under section 26(6) of the OER Act 1995. However
it is made clear that in case of such reduction a fresh
notification under section 26(5) of the OER Act will be
made by the licensees with the approval of OERC.
|
|
6.45.7
|
Finally, the Commission orders
as follows with reference to the prayers of the applicant.
The Commission does not approve the retail supply tariff
as proposed by WESCO for 2001-02 and rejects the tariff
revision proposal.
|
|
6.45.8
|
The Commission also does not
approve the revenue requirement for the FY 2002-03 as proposed
by WESCO and directs for implementation of Retail Supply
Tariff as determined by the Commission in this order to
be effective after expiry of seven days of the publication
by the licensee under section 26(5) of the OER Act 1995.
|
|
6.45.9
|
In case the recommendations
made by the Commission for necessary correctives for determination
of revenue requirement are accepted in toto by the Government,
the retail supply tariff as approved by OERC in order dated.19.01.2001
shall continue unchanged after 31.07.2002.
|
|
6.45.10
|
Pursuant to order dated 19.04.2002
of the Hon'ble High Court of Orissa the order is not being
notified to WESCO in terms of section 26(6) but is filed
in sealed cover in the Hon'ble High Court of Orissa.
The application of M/s WESCO is disposed off accordingly.
|
Sd/-
(B.C. JENA)
M E M B E R
|
Sd/-
(H. SAHU)
M E M B E R
|
Sd/-
(D. C. SAHOO)
CHAIRMAN
|
|