RETAIL SUPPLY TARIFF EFFECTIVE FROM 1st APRIL, 2010 |
Sl. No. |
Category of Consumers |
Voltage of Supply |
Demand Charge (Rs./KW/ Month)/ (Rs./KVA/ Month) |
Energy Charge (P/kWh) |
Customer Service Charge (Rs./Month) |
Monthly Minimum Fixed Charge for first KW or part (Rs.) |
Monthly Fixed Charge for any additional KW or part (Rs.) |
Rebate (P/kWh)/ DPS |
|
LT Category |
1 |
Domestic |
|
|
|
|
|
|
|
1.a |
Kutir Jyoti < 30U/month |
LT |
FIXED MONTHLY CHARGE ----> |
30 |
|
|
1.b |
Others |
|
|
|
|
|
|
10 |
|
(Consumption <= 100 units/month) |
LT |
|
140 |
|
20 |
15 |
|
|
(Consumption >100, <=200 units/month) |
LT |
|
310 |
|
20 |
15 |
|
|
(Consumption >200 units/month) |
LT |
|
310 |
|
20 |
15 |
|
2 |
General Purpose < 110 KVA |
|
|
|
|
|
|
10 |
|
(Consumption <=100 units/month) |
LT |
|
420 |
|
30 |
25 |
|
|
(Consumption >100, <=300 units/month) |
LT |
|
530 |
|
30 |
25 |
|
|
(Consumption >300 units/month) |
LT |
|
590 |
|
30 |
25 |
|
3 |
Irrigation Pumping and Agriculture |
LT |
|
110 |
|
20 |
10 |
10 |
4 |
Allied Agriculture Activities |
LT |
|
120 |
|
20 |
10 |
10 |
5 |
Allied Agro Industrial Actiivities |
LT |
|
320 |
|
80 |
50 |
DPS/Rebate |
6 |
Public Lighting |
LT |
|
420 |
|
20 |
15 |
DPS/Rebate |
7 |
L.T. Industrial (S) Supply |
LT |
|
420 |
|
40 |
35 |
10 |
8 |
L.T. Industrial (M) Supply |
LT |
|
420 |
|
80 |
50 |
DPS/Rebate |
9 |
Specified Public Purpose |
LT |
|
420 |
|
50 |
50 |
DPS/Rebate |
10 |
Public Water Works and Swerage Pumping<110 KVA |
LT |
|
420 |
|
50 |
50 |
10 |
11 |
Public Water Works and Swerage Pumping >=110 KVA |
LT |
200 |
420 |
30 |
|
|
10 |
12 |
General Purpose >= 110 KVA |
LT |
200 |
420 |
30 |
|
|
DPS/Rebate |
13 |
Large Industry |
LT |
200 |
420 |
30 |
|
|
DPS/Rebate |
|
HT Category |
14 |
Bulk Supply - Domestic |
HT |
10 |
410 |
250 |
|
|
10 |
15 |
Irrigation |
HT |
30 |
100 |
250 |
|
|
10 |
16 |
Allied Agro Activities |
HT |
30 |
110 |
250 |
|
|
10 |
17 |
Allied Agro Industrial Activities |
HT |
50 |
310 |
250 |
|
|
DPS/Rebate |
18 |
Specified Public Purpose |
HT |
50 |
As indicated in the notes below. |
250 |
|
|
DPS/Rebate |
19 |
General Purpose >70 and < 110 KVA |
HT |
50 |
250 |
|
|
10 |
20 |
H.T .Industrial (M) Supply |
HT |
50 |
250 |
|
|
DPS/Rebate |
21 |
General Purpose >= 110 KVA |
HT |
200 |
250 |
|
|
DPS/Rebate |
22 |
Public Water Works & Swerage Pumping |
HT |
200 |
250 |
|
|
10 |
23 |
Large Industry |
HT |
200 |
250 |
|
|
DPS/Rebate |
24 |
Power Intensive Industry |
HT |
200 |
250 |
|
|
DPS/Rebate |
25 |
Ministeel Plant |
HT |
200 |
250 |
|
|
DPS/Rebate |
26 |
Railway Traction |
HT |
200 |
250 |
|
|
DPS/Rebate |
27 |
Emergency Supply to CPP |
HT |
0 |
530 |
250 |
|
|
DPS/Rebate |
27 |
Colony Consumption |
HT |
0 |
410 |
0 |
|
|
DPS/Rebate |
|
EHT Category |
29 |
General Purpose |
EHT |
200 |
As indicated in the notes below. |
700 |
|
|
DPS/Rebate |
30 |
Large Industry |
EHT |
200 |
700 |
|
|
DPS/Rebate |
31 |
Railway Traction |
EHT |
200 |
700 |
|
|
DPS/Rebate |
32 |
Heavy Industry |
EHT |
200 |
700 |
|
|
DPS/Rebate |
33 |
Power Intensive Industry |
EHT |
200 |
700 |
|
|
DPS/Rebate |
34 |
Ministeel Plant |
EHT |
200 |
700 |
|
|
DPS/Rebate |
35 |
Emergency Supply to CPP |
EHT |
0 |
510 |
700 |
|
|
DPS/Rebate |
36 |
Colony Consumption |
EHT |
0 |
410 |
0 |
|
|
DPS/Rebate |
Note:
Energy Charges for HT & EHT Consumers
Load Factor (%) |
HT |
EHT |
up to 50% |
375 p/u |
370 p/u |
>50% = <60% |
330 p/u |
325 p/u |
>60% |
280 p/u |
280 p/u |
For details, the orders of the Commission may be referred.
Note:
(i)The energy charge for consumption <=100 units per month in domestic category in LT has remained unchanged for FY 2010-11.
(ii) The tariffs for “irrigation pumping and agriculture” and allied agricultural activities have also remained unchanged for FY 2010-11.
(iii) The reconnection charges have remained unaltered.
(iv) The meter rent has been revised w.e.f. 01.04.2010 as follows:
Type Of Meter |
Revised Meter Rent(Rs.) |
1. Single phase electro magnetic Kwh meter |
20 |
2. Three phase electro magnetic Kwh meter |
40 |
| 3. Three phase electro magnetic trivector meter |
1000 |
| 4. Trivector meter for Railway Traction |
1000 |
| 5. Single phase Static Kwh meter |
40 |
| 6. Three Phase Static Kwh meter 150 |
150 |
| 7. Three phase Static Trivector meter |
1000 |
| 8. Three phase Static Bivector meter |
1000 |
No meter rent shall be payable after the full cost of the meter is recovered.
(v) Prospective small consumers requiring new connection upto and including 3 KW load shall only pay a flat charge of Rs.1000/- as service connection charges towards new connection excluding security deposit as applicable as well as processing fee of Rs.25/-. The service connection charges includes the cost of material and supervision charges.
(vi) In case of installation with static meter/meter with provision of recording demand, the recorded demand rounded to nearest 0.5 KW shall be considered as the contract demand requiring no verification irrespective of the agreement. Therefore, for the purpose of calculation of Monthly Minimum Fixed Charge (MMFC) for the connected load below 110 KVA, the above shall form the basis.
(vii) The billing demand in respect of consumer with Contract Demand of less than 110 KVA having static meters should be the highest demand recorded in the meter during the Financial Year irrespective of the Connected Load, which shall require no verification.
(viii) Three phase consumers with static meters are allowed to avail TOD rebate excluding Public Lighting and emergency supply to CGP @10 paise/unit for energy consumed during off peak hours. Off peak hours has been defined as 12 Midnight to 6 AM of next day.
(ix) Drawl by the industries during off-peak hours upto 120% of Contract Demand without levy of any penalty has been allowed. “Off-peak hours” for the purpose of tariff is defined as from 12 Midnight to 6.00 A.M. of the next day. The consumers who draw beyond their contract demand during hours other than the off-peak hours shall not be eligible for this benefit. When Statutory Load Regulation is imposed then restricted demand shall be treated as contract demand.
(x) General purpose consumers with Contract Demand (CD) < 70 KVA shall be treated as LT consumers for tariff purposes irrespective of level of supply voltage. As per Regulation 76 (1) (c) of OERC Distribution (Condition of Supply) Code, 2004 the supply for load above 5 KW upto and including 70 KVA shall be in 2-phase, 3-wires or 3-phase, 3 or 4 wires at 400 volts between phases.
(xi) Power factor incentive for HT & EHT consumers will be applicable above power factor of 97% and power factor penalty shall be applicable below the level of 92% w.e.f. 01.04.2010.
(xii) Special Tariff for industries of contract demand 100 MVA and above and guaranteed monthly off-take of 80% shall pay a consolidated energy charge of 330 paise per unit.
(xiii) The printout of the record of the static meter relating to MD, PF, number and period of interruption shall be supplied to the consumer wherever possible with a payment of Rs.500/- by the consumer for monthly record.
(xiv) Tariff as approved shall be applicable in addition to other charges as approved in this Tariff order w.e.f. 01.04.2010.
|